Procurement against the class survey clock: how the five-year cycle of annual, intermediate and special surveys plus the two-dockings rule shapes what a vessel must buy and when, the standard drydock material list from anodes and sea valves to chain and coatings, long-lead items that must be ordered months before the yard, machinery scopes (CMS/PMS) that ride the same window, the documentation stack — class certificates, EN 10204 material certs, MED wheelmark where it applies — and a timeline template that turns a docking specification into clean RFQs instead of air-freight emergencies.
| Event | When | Typical scope | Material shadow |
|---|---|---|---|
| Annual survey | Each year, ±3 months window | General condition, safety equipment, selected systems | LSA/FFE consumables, spares top-up, deficiencies from last year closed |
| Intermediate survey | Between 2nd and 3rd anniversary | Enhanced scope; for many ship types, equivalent of a docking (often done in-water where allowed) | Sea-chest and valve attention, anodes check/renewal, ballast tank coatings review |
| Special / renewal survey | Every 5 years | Full renewal of class: hull thickness gauging, machinery, systems | The big list: steel/thickness-driven renewals, valve overhauls, chain calibration, major machinery scopes |
| Dry-docking | Twice per 5-year period (one may be UWILD for eligible vessels) | Hull, propeller, rudder, sea valves, paint | Anodes, coatings, sea/overboard valves, stern-tube seals, hull appendage hardware |
| CMS / PMS machinery items | Continuous, each item on its own interval | Machinery opened on rotation or on approved planned-maintenance credit | Scheduled kits per machine — the separator and turbo patterns |
Exact windows and eligibility (UWILD, PMS credit, ESP for tankers/bulkers) come from the ship's own class status report — the procurement point is simpler: every one of these dates is known years ahead, and each converts into a parts list with a deadline.
| System | Typical lines | Notes |
|---|---|---|
| Hull protection | Sacrificial anodes (hull, sea chests, rudder, tanks), ICCP parts | Count and weight from the docking spec / last report — see the cathodic protection guide |
| Sea water system | Sea and overboard valves (overhaul kits or renewals), sea chest gratings, strainer baskets and gaskets | Survey wants them opened — order kits for all, renewals for the condemned; see valve sourcing |
| Propulsion | Stern-tube/tailshaft seal service, propeller work consumables, rope guard hardware | Tailshaft survey items are the classic long-lead trap |
| Coatings | Antifouling and anticorrosive systems, surface prep consumables | Volumes from the paint spec; owner-supply vs yard-supply decided early |
| Anchoring/mooring | Chain (calibration/renewal lengths), shackles, windlass brake parts, mooring ropes | Certified items — paper matters as much as steel |
| Machinery riding the window | Cooler retubes/gaskets, pump overhauls (seals), separator and turbo scopes, boiler work | Not strictly docking items — but the only time the plant is cold |
| Piping renewals | Spools, flanges, gaskets (material guide), bolting | Thickness-gauging outcomes drive quantities — hold a contingency allowance |
| Safety/statutory | LSA servicing, fixed fire system parts, 15 ppm separator/OCM compliance items | Certificate-bound; servicing stations booked with the yard slot |
| When (before yard arrival) | Procurement action |
|---|---|
| 6–12 months | Docking specification drafted; long-lead census: tailshaft seals, large/exotic valves, class-certificate machinery parts, chain. RFQs out for everything over ~8 weeks lead |
| 4–6 months | Yard chosen; owner-supply vs yard-supply split fixed; anodes, valves, coatings ordered; machinery kits (CMS items riding the window) ordered to plate data |
| 2–3 months | Consolidated balance RFQ: gaskets, bolting, strainers, consumables, tools; certificates chased and filed against each line |
| 4–8 weeks | Deliveries converge on the yard or last convenient port; packing lists mirror the spec item numbers; contingency stock (gaskets, bolting, anodes margin) confirmed |
| Yard period | Only genuine findings bought express (thickness-gauging surprises, opened-up condemnations) — with the routine list already on the quay, the air-freight budget serves discoveries, not forgetfulness |
| After | Close-out: unused stock back to inventory with certs attached; lessons into the next spec — quantities corrected by what the ship actually consumed |
The quiet money-saver in that table is the delivery-point decision made early: owner-supplied material to the yard gate (customs-cleared, marked per spec item) against last-port delivery where the yard's import regime is painful. Both are routine for a supplier who knows the job is a docking — which is why the RFQ should say so.
Three layers, requested per line rather than discovered at survey. Material certificates: EN 10204 3.1 as the working default for pressure parts, chain-and-lifting and structural items; 3.2 where class witnesses. Product approvals: class type approval where the system demands it, MED wheelmark for the EU-flag statutory equipment list, and the engine/machinery makers' documentation for survey-credited scopes. Traceability: heat numbers matching certs, certificates filed against the docking-spec item numbers so the surveyor's question ("show me the paper for this valve") is a thirty-second answer. Our practice: certificates attached line-by-line to the delivery, and the whole file to the office in one package — the HS-code layer for customs rides the same structure.
How buying works at cballast. Send the docking specification or even its draft — we translate it into structured RFQ lines, flag the long-lead and certificate-bound items with dates, quote consolidated to yard or last port, and hold the paper trail per item number. Accounts are vetted at onboarding; first order prepaid; established accounts on credit terms with repeat discounts; public bodies and utilities invoiced against purchase order from the first order. RFQs to sales@cballast.com.
Standards and sources referenced: IACS classification survey scheme (annual / intermediate / special surveys, docking requirements, UWILD and PMS arrangements per society rules); SOLAS statutory survey framework; EN 10204; MED (2014/90/EU) equipment regime. Specific windows and eligibility always per the vessel's own class status.
Questions on a docking list or a long-lead census: write to sales@cballast.com. We answer whether or not you buy from us.