Procurement against the class survey clock: how the five-year cycle of annual, intermediate and special surveys plus the two-dockings rule shapes what a vessel must buy and when, the standard drydock material list from anodes and sea valves to chain and coatings, long-lead items that must be ordered months before the yard, machinery scopes (CMS/PMS) that ride the same window, the documentation stack — class certificates, EN 10204 material certs, MED wheelmark where it applies — and a timeline template that turns a docking specification into clean RFQs instead of air-freight emergencies.

The short version

1. The survey cycle and its material shadow

EventWhenTypical scopeMaterial shadow
Annual surveyEach year, ±3 months windowGeneral condition, safety equipment, selected systemsLSA/FFE consumables, spares top-up, deficiencies from last year closed
Intermediate surveyBetween 2nd and 3rd anniversaryEnhanced scope; for many ship types, equivalent of a docking (often done in-water where allowed)Sea-chest and valve attention, anodes check/renewal, ballast tank coatings review
Special / renewal surveyEvery 5 yearsFull renewal of class: hull thickness gauging, machinery, systemsThe big list: steel/thickness-driven renewals, valve overhauls, chain calibration, major machinery scopes
Dry-dockingTwice per 5-year period (one may be UWILD for eligible vessels)Hull, propeller, rudder, sea valves, paintAnodes, coatings, sea/overboard valves, stern-tube seals, hull appendage hardware
CMS / PMS machinery itemsContinuous, each item on its own intervalMachinery opened on rotation or on approved planned-maintenance creditScheduled kits per machine — the separator and turbo patterns

Exact windows and eligibility (UWILD, PMS credit, ESP for tankers/bulkers) come from the ship's own class status report — the procurement point is simpler: every one of these dates is known years ahead, and each converts into a parts list with a deadline.

2. The standard docking material list

SystemTypical linesNotes
Hull protectionSacrificial anodes (hull, sea chests, rudder, tanks), ICCP partsCount and weight from the docking spec / last report — see the cathodic protection guide
Sea water systemSea and overboard valves (overhaul kits or renewals), sea chest gratings, strainer baskets and gasketsSurvey wants them opened — order kits for all, renewals for the condemned; see valve sourcing
PropulsionStern-tube/tailshaft seal service, propeller work consumables, rope guard hardwareTailshaft survey items are the classic long-lead trap
CoatingsAntifouling and anticorrosive systems, surface prep consumablesVolumes from the paint spec; owner-supply vs yard-supply decided early
Anchoring/mooringChain (calibration/renewal lengths), shackles, windlass brake parts, mooring ropesCertified items — paper matters as much as steel
Machinery riding the windowCooler retubes/gaskets, pump overhauls (seals), separator and turbo scopes, boiler workNot strictly docking items — but the only time the plant is cold
Piping renewalsSpools, flanges, gaskets (material guide), boltingThickness-gauging outcomes drive quantities — hold a contingency allowance
Safety/statutoryLSA servicing, fixed fire system parts, 15 ppm separator/OCM compliance itemsCertificate-bound; servicing stations booked with the yard slot

3. The timeline template

When (before yard arrival)Procurement action
6–12 monthsDocking specification drafted; long-lead census: tailshaft seals, large/exotic valves, class-certificate machinery parts, chain. RFQs out for everything over ~8 weeks lead
4–6 monthsYard chosen; owner-supply vs yard-supply split fixed; anodes, valves, coatings ordered; machinery kits (CMS items riding the window) ordered to plate data
2–3 monthsConsolidated balance RFQ: gaskets, bolting, strainers, consumables, tools; certificates chased and filed against each line
4–8 weeksDeliveries converge on the yard or last convenient port; packing lists mirror the spec item numbers; contingency stock (gaskets, bolting, anodes margin) confirmed
Yard periodOnly genuine findings bought express (thickness-gauging surprises, opened-up condemnations) — with the routine list already on the quay, the air-freight budget serves discoveries, not forgetfulness
AfterClose-out: unused stock back to inventory with certs attached; lessons into the next spec — quantities corrected by what the ship actually consumed

The quiet money-saver in that table is the delivery-point decision made early: owner-supplied material to the yard gate (customs-cleared, marked per spec item) against last-port delivery where the yard's import regime is painful. Both are routine for a supplier who knows the job is a docking — which is why the RFQ should say so.

4. Documentation — what must accompany the steel

Three layers, requested per line rather than discovered at survey. Material certificates: EN 10204 3.1 as the working default for pressure parts, chain-and-lifting and structural items; 3.2 where class witnesses. Product approvals: class type approval where the system demands it, MED wheelmark for the EU-flag statutory equipment list, and the engine/machinery makers' documentation for survey-credited scopes. Traceability: heat numbers matching certs, certificates filed against the docking-spec item numbers so the surveyor's question ("show me the paper for this valve") is a thirty-second answer. Our practice: certificates attached line-by-line to the delivery, and the whole file to the office in one package — the HS-code layer for customs rides the same structure.

How buying works at cballast. Send the docking specification or even its draft — we translate it into structured RFQ lines, flag the long-lead and certificate-bound items with dates, quote consolidated to yard or last port, and hold the paper trail per item number. Accounts are vetted at onboarding; first order prepaid; established accounts on credit terms with repeat discounts; public bodies and utilities invoiced against purchase order from the first order. RFQs to sales@cballast.com.

Frequently asked questions

What spare parts are needed for a dry-docking?
The predictable core: hull and sea-chest anodes, sea/overboard valve overhaul kits and renewals, stern-tube seal service parts, coatings, strainer internals, gaskets and bolting, chain work, plus whatever machinery scopes ride the cold-plant window (separator majors, turbo scopes, cooler gaskets). The docking specification turns this into counted lines months ahead.
How often is a special survey and what does it mean for purchasing?
Every five years (renewal of class), with an intermediate survey between the 2nd and 3rd anniversary and two dockings per cycle. For purchasing it means the heaviest material list of the cycle lands on a known date — thickness-driven steel and pipe renewals, full valve programmes, certified chain — and the long-lead items on it must be ordered a quarter ahead.
What are long-lead items in a docking?
Anything that cannot be produced or certified inside the yard's notice period: tailshaft/stern-tube seals, large or exotic-material valves, class-witnessed (3.2) material, chain lengths with certificates, major machinery parts bound to serial numbers. Census them when the spec is drafted — 8 to 16 weeks before the yard is the safe order window.
Should material be delivered to the yard or carried on board?
Both patterns work; decide early and tell the supplier. Yard-gate delivery wants customs handled and every package marked with the spec item number; last-port delivery suits paint, anodes and robust hardware the crew can stow. The expensive pattern is deciding late and flying what could have sailed.
What documentation do survey parts need?
Per line: EN 10204 material certificates (3.1 standard, 3.2 where class witnesses), type approval or MED wheelmark where the equipment category demands it, and heat/serial traceability matching the paper. The surveyor accepts parts with paper; parts without paper become findings.
Can one supplier handle a whole docking list?
That is the point of consolidation: one structured RFQ, one freight plan, one certificate file, long-lead risk flagged in the first response rather than discovered in week minus one. cballast.com runs dockings exactly this way — send the specification draft to sales@cballast.com and the translation into clean lines comes back with the quote.

References and related guides

Standards and sources referenced: IACS classification survey scheme (annual / intermediate / special surveys, docking requirements, UWILD and PMS arrangements per society rules); SOLAS statutory survey framework; EN 10204; MED (2014/90/EU) equipment regime. Specific windows and eligibility always per the vessel's own class status.

Questions on a docking list or a long-lead census: write to sales@cballast.com. We answer whether or not you buy from us.

Open / Download PDF

Compiled by cBallast for identification and cross-reference. Part numbers, designations and trademarks belong to their respective manufacturers. Confirm ratings and dimensions against the manufacturer's current documentation and the nameplate of the installed equipment before ordering or installation.