UV Lamps, Sleeves and Sensors — Certificate-Bound Buying

Procurement guide compiled by cBallast. 9-page PDF; the full content is on this page.
Compiled by
cBallast
Subject
UV disinfection systems
Document type
Procurement guide
Reference
2026 edition
Issued
2026-11-04
Pages
9
Format
Web page and PDF

How waterworks, wastewater plants, fish farms, pools and ships buy UV lamps, quartz sleeves and sensors by the hundred: the standards that name the lamp (DVGW, ÖNORM, USEPA, NSF, IMO), lamp technology decoded, the RoHS and sanctions clauses a 2026 tender needs, the annual-bill arithmetic and the lamp-set standing list.

The short version

1. Where UV sits, and who buys it

SegmentWhat UV does thereGoverning rulesWho buysWhat drives consumable volume
Municipal drinking waterSecond hygienic barrier against Cryptosporidium and Giardia; in Norway the usual barrier beside filtration under the drinking water regulationDVGW W 294, ÖNORM M 5873, USEPA UVDGM and LT2ESWTR, NSF/ANSI 55, EU Drinking Water Directive 2020/2184Municipal and intermunicipal waterworks, public utilitiesReactors run continuously; lamp changes on rated hours; sensor calibration on a fixed cycle
Municipal and industrial wastewaterFinal effluent disinfection, water reuse, combined sewer overflowDischarge permits; USEPA and state criteria; EU water reuse Regulation 2020/741Public wastewater utilities, industrial plantsOpen-channel banks of hundreds to thousands of lamps; the largest lamp populations anywhere
AquacultureIntake and recirculation water in hatcheries, smolt plants and RAS; effluentVeterinary and biosecurity rules; in Norway the Food Safety Authority's requirementsPrivate operators, often large groupsMany mid-size reactors per site; continuous duty; seawater fouling
Swimming poolsChloramine reduction and disinfection with medium-pressure UVDIN 19643 process combinations; national pool hygiene rulesMunicipalities, leisure centres, hotelsMedium-pressure lamps with short rated lives
Ships: ballast waterTreatment to the IMO D-2 standard in UV-based systemsIMO BWM Convention and BWMS Code; USCG type approvalShip owners and managersLamp sets per system, replaced on hours, bought per vessel class
Food, beverage, pharma, electronicsDisinfection of process water, dechlorination, TOC reduction with 185 nm lamps, ozone destructionSite quality systems; pharmacopoeia water requirementsPrivate plantsContinuous duty; high-purity sleeves and lamps; validation documents

The public-sector weight is the point of the table. Most of the large lamp populations sit in municipal water and wastewater, and most of them are bought under procurement law. That changes how a supplier has to sell (section 8) more than it changes what is sold.

2. The reactor as a parts list

ComponentFunctionTypical replacementWhat identifies it
UV lampThe UV-C sourceAt rated hours: roughly 9,000 to 12,000 h for standard low-pressure, 12,000 to 16,000 h for amalgam low-pressure high-output, 4,000 to 10,000 h for medium-pressure, as the maker specifiesLamp maker and type, or reactor maker's part number; arc length, base, power
Quartz sleeveSeparates lamp from water; transmits UV-CEvery second or third lamp change, or on inspection: fouling, etching, cracksLength, outer diameter, wall, closed or open end, quartz grade
O-rings and sealsSeal sleeve to reactor; seal lamp holderAt every lamp changeSize and compound: EPDM, FKM, silicone; food-contact or drinking-water approval
Ballast or electronic power supplyDrives the lamp at its rated currentYears; on failure or on lamp-type changeReactor maker's part number; lamp type and count it drives
UV intensity sensor (duty sensor)Continuous measurement behind the sleeveReplace when the duty-to-reference ratio drifts; recalibrate on cycleReactor maker's type; DVGW or ÖNORM-conforming sensor where certified
Reference sensorOffline check of the duty sensorsFactory calibration at least every three yearsCertified reference radiometer type
Wiper systemMechanical sleeve cleaningWiper rings yearly or on wear; drives and seals on inspectionReactor maker's part numbers
Cleaning chemicalsChemical sleeve cleaning in situPer cleaning cycleCitric, oxalic or phosphoric acid solutions as the maker specifies
UVT monitor, flow meter, controller partsDose controlOn failure or obsolescenceInstrument maker's part numbers

The lamp set is lamp, sleeve and the O-rings for one lamp position. Buying in lamp sets removes the most common failure on a change-out day, which is a shelf full of lamps and one missing O-ring size.

3. Lamp technology decoded

Low-pressure (LP) mercury lamps emit almost entirely at 254 nm, run at low power per lamp and have the highest conversion of electrical power to UV-C. They dominate small and medium reactors.

Low-pressure high-output amalgam lamps (LPHO) hold mercury as an amalgam, which keeps output stable over a wider water-temperature range and allows several times the UV-C output of a standard LP lamp of the same length, at 12,000 to 16,000 rated hours on electronic ballasts. They dominate municipal drinking water and wastewater reactors and most new aquaculture installations.

Medium-pressure (MP) lamps emit a broad spectrum from 200 nm upward at high power per lamp, with lower conversion efficiency and shorter life. They give compact reactors for high flows and poor transmittance, and they are the standard in pools because the broad spectrum breaks down chloramines.

UV-C LEDs are established in point-of-use and small appliance units and in some instrument applications; at municipal flows the lamp reactors above remain the installed base and the current purchasing reality.

What a lamp designation encodes. Arc length and overall length; tube diameter (T5, T6, T8, T10 and others); base and pin configuration (single-ended four-pin, double-ended two-pin, and maker-specific bases); electrical rating (watts and lamp current); amalgam or standard; quartz type (ozone-generating 185 nm or ozone-free). Lamp makers such as Signify (Philips TUV ranges), Heraeus, LightSources and LightTech, Ushio and OSRAM supply both their own catalogue types and lamps built to reactor makers' specifications; a reactor maker's part number may map to one lamp maker's type, or to a lamp made only for that reactor.

The ballast must match the lamp. A lamp runs at the current and ignition conditions its ballast or electronic power supply was built for. A lamp of the right dimensions on the wrong ballast runs outside its rating, which shortens life and changes output; the validated dose assumed the rated output.

End-of-lamp-life. Makers specify the fraction of initial UV-C output remaining at rated hours, and the reactor's certified or validated dose is calculated at that end-of-life output together with sleeve fouling and ageing. Lamps run past rated hours take the reactor outside the basis of its certificate even when the sensor still reads above alarm, which is why lamp hours, not sensor readings alone, drive the change-out calendar in certified plants.

4. The certificate-bound consumable

A UV reactor earns its place in a drinking-water plant by a biodosimetric test: the reactor is challenged with a test organism and the result is expressed as a reduction equivalent dose (RED). DVGW W 294 and ÖNORM M 5873 require an RED of 40 mJ/cm² for drinking water, and NSF/ANSI 55 Class A certifies a dose at least equivalent to 40 mJ/cm² at the alarm set point. The USEPA UVDGM validates reactors against the dose table of the LT2 rule, which assigns 12 mJ/cm² for 3-log Cryptosporidium and 186 mJ/cm² for 4-log virus credit on the adenovirus basis. The test is run with a specific lamp type, a specific sleeve, a specific sensor and a specific control logic, and the certificate or validation report names them.

That makes four consumables certificate-bound:

The same logic binds the lamp in a ballast water system: the IMO type approval under the BWMS Code and the USCG type approval cover the system as tested, lamp type included. Spares for a type-approved system are the maker's listed spares.

Where equivalents are legitimate. Positions not bound by a certificate: process water, many aquaculture and effluent duties, pools outside a DIN 19643 process-combination claim, industrial reuse, and any reactor whose maker has listed an alternative lamp type. There the test is technical: same arc length, overall length, diameter and base; same electrical rating and lamp current on the existing ballast; same or higher UV-C output at the stated hours; same quartz type (ozone-free where the original was); same amalgam or standard construction; and a lamp maker's written equivalence statement. Lamp makers publish cross-references for the common reactor types; a reactor maker's own replacement is the reference the equivalent is measured against.

Our rule. For a reactor that holds a DVGW, ÖNORM, USEPA or NSF certificate, or an IMO or USCG type approval, we quote the lamp type the certificate names, or an alternative the reactor maker has listed, and nothing else. For unbound positions we may quote an equivalent to the specification above, declared on the quote next to the original, never swapped silently.

5. The standards map

Standard or ruleScopeWhat it fixes for purchasing
DVGW W 294-1 to -3 (Germany)UV systems for drinking water: requirements, testing, sensors40 mJ/cm² RED; certified reactor with named lamp and sensor; reference sensor regime
ÖNORM M 5873-1 and -2 (Austria)Low-pressure (-1) and medium-pressure (-2) drinking-water reactors40 mJ/cm² RED; ÖVGW certification; accepted widely in Europe including Norway
USEPA UVDGM 2006 with LT2ESWTR (USA)Validation of reactors for Cryptosporidium, Giardia and virus creditValidated dose and operating envelope per reactor; the lamp and sensor as validated
NSF/ANSI 55 (USA)Point-of-entry and point-of-use UVClass A at 40 mJ/cm² equivalent for potable use; Class B for supplemental treatment only
EU Drinking Water Directive 2020/2184Quality and risk-based approach for water intended for human consumptionNational transposition; materials in contact with drinking water under the Directive's harmonised approach
EU Regulation 2020/741Water reuse for agricultural irrigationReuse classes that UV effluent disinfection is sized against
DIN 19643 (Germany)Treatment of pool and bath waterUV within approved process combinations for chloramine reduction
IMO BWM Convention, D-2 and the BWMS Code; USCG 46 CFR 162.060Ballast water treatment systemsType-approved system as tested, lamp type included
EU RoHS Directive 2011/65, Annex III exemptions 4(a)-I and 4(f)-IVMercury in UV-C low-pressure and amalgam lamps (4(a)-I) and in medium- and high-pressure UV lamps (4(f)-IV)Legal basis for mercury UV lamps on the EU market; see section 8
EU WEEE Directive 2012/19Collection and treatment of spent lampsTake-back and hazardous-waste routing for mercury lamps
EU Directive 2014/55 and the European e-invoicing standardElectronic invoicing in public procurementPublic buyers accept e-invoices to EN 16931; Norway requires EHF (Peppol BIS) from suppliers to the public sector
EU Directive 2011/7Late paymentPublic authorities pay within 30 days as a rule
Regulation (EU) 833/2014, Article 5kSanctions in public procurementNo award to Russian-established or Russian-majority-owned suppliers, nor reliance on them for more than 10% of contract value

6. Sensors and monitoring: the part of the budget nobody forecasts

A certified plant runs two kinds of sensor. Duty sensors sit in the reactor and measure continuously. A reference sensor is kept offline and used to check the duty sensors; the drinking-water guidance that follows DVGW and ÖNORM practice checks duty against reference at least monthly, replaces or corrects a duty sensor whose ratio to the reference exceeds 1.2, and sends the reference sensor for factory calibration against a traceable standard at least every three years.

For purchasing, that means three lines that recur as predictably as lamps: duty sensors on a replacement cycle, reference-sensor calibration on a three-year cycle, and sensor windows and O-rings at each service. They belong on the standing list next to the lamp sets, because a plant without a valid reference sensor is a plant that cannot prove its dose.

7. The annual bill

For each reactor: lamp count, rated lamp life, operating hours per year.

 lamps per year  =  lamp count  x  operating hours per year  /  rated hours
 sleeves per year  =  lamp count  /  sleeve life in lamp changes  x  lamp changes per year
 O-ring sets per year  =  lamps per year

A wastewater bank of 1,000 amalgam lamps rated at 12,000 hours and running all year replaces around 730 lamps a year on hours alone; with dose pacing (lamps switched by flow and transmittance) fewer, with a fixed annual change-out campaign exactly 1,000. A waterworks with eight reactors of 24 lamps each replaces about 140 lamps a year. Sleeves follow at a third to a half of that, O-rings one set per lamp, plus sensors and wipers on their own cycles. The bill for a large plant is six figures a year in consumables alone, every year, for the life of the plant, which is why it belongs in a framework agreement and not in a monthly purchase order.

Two levers reduce it without touching the dose. Dose pacing, where the control system runs only the lamps the flow and transmittance need, extends lamp life in hours. Scheduled sleeve cleaning, mechanical or chemical, keeps the fouling factor where the validation assumed it, which keeps the dose at the lamps' rated hours instead of forcing early changes.

8. Buying UV consumables under public procurement

Thresholds. From 1 January 2026 to 31 December 2027 the EU thresholds for supplies and services are EUR 140,000 for central government authorities and EUR 216,000 for sub-central authorities under Directive 2014/24, and EUR 432,000 under the utilities Directive 2014/25 (Delegated Regulations 2025/2152 and 2025/2150). Norway applies the equivalent EEA thresholds from 21 April 2026 at NOK 1.63 million for central government, NOK 2.5 million for other contracting authorities and NOK 5 million for utilities, with a national announcement threshold of NOK 1.3 million below them. A multi-year lamp supply for a large plant crosses these lines, which means a published notice on TED or Doffin, a formal procedure and a framework.

The right instrument. A framework agreement of two to four years with call-offs per change-out campaign, priced on unit rates with quantity bands per lamp type and sleeve type, is the instrument that fits consumables. Dynamic purchasing systems suit buyers that aggregate several plants. A single-reactor replacement of lamps and sleeves, under the thresholds, is a direct purchase against a quote.

Specifying without unlawful lock-in. Directive 2014/24 Article 42 forbids technical specifications that refer to a specific make or source unless the subject matter justifies it, and requires the words "or equivalent" when such a reference is made. For a certificate-bound position the justification exists and should be written down: "lamp type as named in the reactor's DVGW/ÖNORM certificate or listed by the reactor manufacturer as an approved alternative". For unbound positions, specify the lamp by its parameters (arc length, overall length, diameter, base, power, lamp current, UV-C output at rated hours, amalgam, ozone-free quartz, rated life) and let equivalents compete.

Clauses a 2026 UV tender needs.

  1. RoHS status. Mercury UV lamps are placed on the EU market under Annex III exemptions 4(a)-I (UV-C low-pressure and amalgam lamps) and 4(f)-IV (medium- and high-pressure UV lamps). The Annex III date for these exemptions is 24 February 2027; renewal requests were due by 24 August 2025 and were filed, the stakeholder consultation ran in mid-2026, and the Commission's decision had not been published at the time of writing. Under Article 5(5) of the Directive an exemption with a timely renewal request remains valid until the decision. The tender should require the bidder to state the exemption each lamp type relies on and to notify the buyer of any change in its status.
  2. Sanctions. Under Article 5k of Regulation (EU) 833/2014, mirrored in Norway's sanctions regulation, no contract above the thresholds may be awarded to a supplier established in Russia or majority-owned from Russia, nor rely on such entities for more than 10% of the contract value as subcontractors or suppliers. The tender should require a declaration of the country of manufacture and the ownership of the maker for every lamp and sleeve type offered.
  3. WEEE and hazardous waste. Spent mercury lamps are hazardous waste under WEEE. The tender should state who takes back spent lamps, how they are packed and transported, and where the treatment certificate is filed.
  4. Documents per line. Certificate reference for certificate-bound items; lamp maker's equivalence statement for equivalents; material declarations for sleeves and O-rings in contact with drinking water; safety data sheets for cleaning chemicals.
  5. Delivery per campaign. Call-off quantities by reactor and date, packed per lamp set, with lamp serial numbers and hours tracking where the plant uses them.
  6. E-invoicing and payment. Peppol BIS or EHF e-invoices to the buyer's access point; payment within 30 days under Directive 2011/7.

The supplier's side of the same rules. A supplier to this market registers on the buyer's portal, completes the European Single Procurement Document, declares origin and ownership down its chain, invoices electronically, and accepts public-sector payment terms. These are not obstacles; they are the entry ticket.

9. Lead time: what is on the shelf and what is not

Standard LP and amalgam lamp types in common lengths, standard quartz sleeves and O-rings are stock items at the lamp makers and at reactor makers' spares desks, and move in days. Medium-pressure lamps, unusual arc lengths, lamps made only for one reactor type, certified sensors and ballasts for older reactors are made or allocated to order and run from weeks to months. The protection is the same as for every other consumable in this series: know which of your positions are in the second group before the change-out campaign, and hold a lamp set per reactor on site.

For plants with several reactors of the same type, a consolidated campaign order with staged delivery per reactor is cheaper and safer than reactor-by-reactor buying: one entry, one document pack, one shelf.

10. The UV register and the standing list

One row per reactor:

 TAG            reactor tag, plant, location
 REACTOR        maker, model, serial, year, certification (DVGW, ÖNORM, USEPA, NSF, IMO) and certificate reference
 LAMPS          lamp type as certified, maker's part number, count, rated hours, hours at last change
 ALTERNATIVES   lamp types listed by the reactor maker as approved, if any
 SLEEVES        part number, count, date of last replacement
 O-RINGS        sizes and compounds per position
 SENSORS        duty sensor type and count; reference sensor type and last factory calibration
 BALLASTS       type and count
 WIPER          wiper ring and seal part numbers, interval
 CAMPAIGN       planned change-out dates
 STOCK          lamp sets on site: quantity, location

The register produces the standing list: annual quantities per lamp type, sleeve type, O-ring set, sensor and wiper part, with the certificate reference per line and the campaign dates. Priced once a year on unit rates with quantity bands, it becomes the schedule of a framework agreement, and the call-offs follow the campaigns. For a fleet, the register is per ballast water system type and the standing list is delivered to the agent at the port where the service is planned.

11. The cballast UV RFQ

Copy it, fill it in and send it to sales@cballast.com. It works with any supplier, and it is built so that one reactor or a whole plant can be priced firm without a clarification round.

 1. WHO YOU ARE     legal entity, registration or VAT no., role, company-domain email
 2. END USER        plant or vessel (IMO no.), or "we are the end user"; public body or private
 3. REACTOR         maker, model, serial, year; certificate or type approval and its reference
 4. LAMPS           type as certified or as marked, maker's part number, quantity; approved alternatives if listed
 5. SLEEVES, SEALS  sleeve part number and quantity; O-ring sizes and compounds; quantity
 6. SENSORS, OTHER  duty and reference sensors, ballasts, wiper parts, cleaning chemicals, with part numbers
 7. EQUIVALENT OK?  certificate-bound (OEM type only) or unbound (equivalents to specification may be offered)
 8. DOCUMENTS       certificate references, equivalence statements, material declarations, SDS, origin and ownership declaration, RoHS exemption reference
 9. DELIVERY        address or port, campaign dates, staged quantities per reactor, Incoterm
10. COMMERCIAL      one-off, annual standing list, or framework schedule; e-invoicing route; payment terms

What comes back from our desk: each line priced with maker, type and certificate status; equivalents, where allowed, declared next to the OEM type with the lamp maker's equivalence statement; lead time per line; origin and ownership stated per maker; documents per line as asked; and, for standing lists, unit rates with quantity bands and a campaign delivery schedule.

12. Accounts, including public ones

Private accounts. Every new account is vetted at onboarding. The first order is prepaid. Established accounts move to credit terms and substantial repeat-account discounts.

Public bodies and utilities. Contracting authorities and public utilities are invoiced against their purchase order on public-sector terms from the first order, by Peppol BIS or EHF e-invoice where the buyer requires it, with the supplier documentation (registration, tax status, origin and ownership declarations, ESPD) provided at onboarding. Framework schedules are priced on unit rates with quantity bands and called off per campaign.

We work on quote and invoice, not a checkout. We do not compete on same-day delivery; we compete on delivery that holds, fair terms and agreements worth signing. The buyers we are built for are end users with recurring demand: waterworks and wastewater utilities, aquaculture operators, pool operators, ship owners and managers, process plants. We do not quote broadcast lists with no named end user.

Frequently asked questions

Can I replace the UV lamps in a certified drinking-water reactor with another maker's lamps?
Only with a lamp type named in the reactor's DVGW, ÖNORM, USEPA or NSF certificate or listed by the reactor maker as an approved alternative. The certificate was earned with that lamp, sensor and sleeve. For reactors without a certificate, an equivalent lamp to the same arc length, base, electrical rating, UV-C output and quartz type, with the lamp maker's equivalence statement, is legitimate.
What UV dose is required for drinking water?
A reduction equivalent dose of 40 mJ/cm² under DVGW W 294 and ÖNORM M 5873, and an equivalent dose under NSF/ANSI 55 Class A. The USEPA UVDGM validates reactors against the LT2 dose table, for example 12 mJ/cm² for 3-log Cryptosporidium credit.
How often are UV lamps, sleeves and sensors replaced?
Lamps at rated hours: roughly 9,000 to 12,000 for standard low-pressure, 12,000 to 16,000 for amalgam, 4,000 to 10,000 for medium-pressure, as the maker specifies. Sleeves every second or third lamp change or on inspection. O-rings at every lamp change. Duty sensors are checked against a reference sensor monthly and replaced when the ratio exceeds 1.2; the reference sensor is factory-calibrated at least every three years.
Are mercury UV lamps still legal in the EU?
Yes. They are placed on the market under RoHS Annex III exemptions 4(a)-I (UV-C low-pressure and amalgam) and 4(f)-IV (medium- and high-pressure). The Annex III date is 24 February 2027, renewal requests were filed by the August 2025 deadline, and the exemptions remain valid until the Commission decides. Tenders should require bidders to state the exemption relied on.
What must a UV lamp tender in the EU or Norway include?
The lamp type per reactor as certified or a parameter specification with "or equivalent"; a declaration of country of manufacture and maker ownership under Article 5k of Regulation (EU) 833/2014; the RoHS exemption reference per lamp type; WEEE take-back of spent lamps; documents per line; staged delivery per campaign; e-invoicing by Peppol BIS or EHF; 30-day payment under Directive 2011/7.
Which companies make UV disinfection reactors and lamps?
Reactor makers include Xylem Wedeco (Germany), Trojan Technologies (Canada), Hanovia and Berson (UK and Netherlands, Halma), atg UV (UK, Xylem), SITA (Italy), LIT (production centre in Erfurt, Germany; group headquartered in Moscow), ProMinent (Germany), BIO-UV (France), UltraAqua (Denmark) and, for ballast water, Alfa Laval PureBallast (Sweden), Optimarin (Norway), Trojan Marinex and BIO-UV BIO-SEA. Lamp makers include Signify (Philips TUV), Heraeus, LightSources and LightTech, Ushio and OSRAM.
Does cballast supply UV lamps, quartz sleeves, sensors and spares for SITA, LIT, Wedeco, Berson, Hanovia, atg UV, UltraAqua, Trojan and ballast water UV systems?
Yes, by reactor maker's part number or lamp maker's type, with certificate status, origin and ownership stated per line, on one quote with the sleeves, O-rings, sensors, ballasts and wiper parts that go with them. Standing lists and framework schedules are priced on unit rates with quantity bands and delivered per change-out campaign. Send the UV RFQ or a register to sales@cballast.com.
Does cballast sell to municipalities and public utilities?
Yes, against purchase order on public-sector terms from the first order, with Peppol or EHF e-invoicing and the supplier documentation public buyers require.
What is cballast not the right source for?
Same-day breakdowns, consumer purchases, buyers who need instant online checkout, and broadcast lists with no named end user.

Terms used in this guide

References and related guides

Standards and sources referenced: DVGW W 294-1…-3; ÖNORM M 5873-1/-2; USEPA UV Disinfection Guidance Manual 2006 and LT2ESWTR; NSF/ANSI 55; Directive (EU) 2020/2184; Regulation (EU) 2020/741; DIN 19643; IMO BWM Convention and BWMS Code; USCG 46 CFR 162.060; RoHS 2011/65/EU Annex III exemptions 4(a)-I and 4(f)-IV; WEEE 2012/19/EU; Regulation (EU) 833/2014 Article 5k; Directives 2014/24/EU, 2014/25/EU, 2014/55/EU and 2011/7/EU; Delegated Regulations (EU) 2025/2150 and 2025/2152 (thresholds).

Questions on a reactor's certificate, a lamp cross-reference, a sensor regime or a tender clause are welcome at sales@cballast.com. We answer whether or not you buy from us. Registers, standing lists and UV RFQs go to sales@cballast.com.

Open / Download PDF

Compiled by cBallast for identification and cross-reference. Part numbers, designations and trademarks belong to their respective manufacturers. Confirm ratings and dimensions against the manufacturer's current documentation and the nameplate of the installed equipment before ordering or installation.